A 1MW/2MWh containerised system for a Dutch industrial park, built inside a 20ft enclosure.

Netherlands — industrial park
Netherlands — industrial park

At a glance

Country
Netherlands
Application
Industrial park
System type
C&I, containerised
System size
1MW / 2MWh Container
Inverter / PCS
2 × Megarevo 500kW
Product used
1MW / 2MWh Container, 2× Megarevo 500kW PCS
Completed
May 2026

Challenge

Dutch industrial users face strict carbon footprint standards alongside volatile time-of-use tariffs, so the park needed scale and grid interaction in one package.

Solution

A standard 20ft container carrying 1MW/2MWh, with two 500kW Megarevo grid-tied inverters running in parallel for redundancy.

Result

The project entered pre-commissioning in May 2026; the IP54 enclosure uses front-to-rear active thermal flow for outdoor siting.

Case record first published on ruibitbess.com.

Project support

Need a configured battery storage solution?

Send your application, location, load profile, and target capacity. We will recommend a suitable Ruibit / Dawnice system and confirm sizing assumptions with you.

Quotation target: 24 working hours for a complete brief. Datasheet and certificate package supplied per configuration.